MGMT627 Assignment # 2 Solution:

Question 1:


Considering a and b

Tell separately in which situation (a or b), either it isscope creep and if it is then of what type?

Answer:

In a highway project, the Govt. is the customer; the construction of the highway was 190 which were then extended to 5 km more. The government wants to increase the project scope. It means the project manager now has to manage the construction of 195 km highway.

In situation a:

In the situation of a, the resources and timeline has been fixed but the scope of the highway increases with the size increases. The deliverable size of the highway was 190 km before, which was further extended and the additional 5 km was added to the first project but the resources remains fixed.

If there isn’t any increase in budget and schedule time, the project team may flow away from the original goals or objectives, as the capacity of the project increases, the project manager needs more task for completing the project in limited resources and limited timeline, which was designed for the smaller project. Due to this the scope creep became effect in overflow of the project's original goals.

For situation b:

In situation b, the additional project is not bad for the project manager because the government is providing extra funds for additional construction and also provides extra time limit for completing the project. So the situation b is not scope creep because the government is providing more funds to be issued and 8 week additional time for the construction.

Question 2:

How this additional construction will affect theWork Breakdown Structure (WBS) of your project?

Answer:



The work breakdown structure of any project is specially made for networking of the project. It contains all the work associated with the project. It divides the whole work of the project into pieces, so that the project manager can better understand the project. The WBS must be flexible, because the

project’s requirements changes every time, and it must be able to use in every circumstances.



Work Breakdown Structure is not a description of the process which will be following to perform the project, it also doesn’t address the schedule which define how and when the deliverables will be produces, rather it is specifically limited to describe and detailing the project’s outcome or scope.



The additional construction of the highway will slightly affect the Work breakdown structure because the project manager will need to describe and make the detailed diagram for handling the construction process. The changes may occur in the scope of the project because of the additional construction but the project manager should clearly define the changes.

HRM627 GDB # 2 Solution:

Vocational education or vocational education and training (VET) prepares trainees for jobs that are based on manual or practical activities, traditionally non-academic, and totally related to a specific trade, occupation, or vocation. It is sometimes referred to as technical education as the trainee directly develops expertise in a particular ** of techniques or technology.
On the other hand
Technology education is a study of technology, which provides an opportunity for students to learn about the processes and knowledge related to technology. As a study, it covers the human ability to shape and change the physical world to meet needs, by manipulating materials and tools with techniques. As education, the goal is to teach the knowledge and techniques to develop technological literacy which is accomplished by bringing laboratory activities to students.

GDB OF MGT 502

MilkyWay Company is using charismatic power.Because charismatic power is an extension referent power stemming from other.


Xyer company is using the Expert power. Because Expert power influence wielded as a result expertise special skill and knowledge.